Nigerian presidency repeats lies, half-truths on infrastructure projects in South-East ( Part 2)

THE second part of the investigation continues to examine the claims of the Presidency Office of Digital Engagement (PODE) on critical infrastructure projects in South-East Nigeria.

ON September 7, 2021, the PODE published what it called ‘a compendium of President Buhari’s ongoing and completed infrastructure projects in South-East Nigeria.’

The list was released two days before Buhari’s visit to Imo State, one of the five states of South-East Nigeria.

You can read the first part here.

The PODE claimed that the Buhari administration was rehabilitating sections 1 and 2 of Abakiliki-Afikpo Road. The ICIR reporter travelled through this road and confirmed that work was going on.

Onueke, along Abakiliki-Afikpo Road, Ebonyi State
Onueke, along Abakiliki-Afikpo Road, Ebonyi State

According to information obtained from the website of the Ministry of Works and from online sources, the work is handled by several contractors, including Uniglobe, Builettine, CCEC, and Kemmasphere Realty Company.

Findings showed that work was going on at Abomegga, Abakiliki, Amuzu and Igboruma axes when The ICIR visited the site, but it was found that Afikpo and Amasiobi areas were wearing off.

However, the Ebonyi State government lays claim on the project. In 2017, President Buhari flew into Ebonyi State and commissioned a 14.5 Kilometer Abakaliki-Afikpo Road, which is exactly the project the Federal Government claims to be rehabilitating. In Nigeria, federal roads are handled by the Federal Government while state roads are repaired or built by the state or subnational governments.

It, therefore, means that neither can claim projects done by the other.

Read Also:

The ICIR sent the Freedom of Information (FOI) letter to the Federal Minister of Works and Housing Babatunde Fashola on January 25, 2022, regarding the status of this project and why it was so. Still, he did not reply to questions posed by the organisation more than one month after.


READ ALSO:

Nigerian presidency repeats lies, half-truths on infrastructure projects in South-East (part 1)

Ariaria Market: Failed power project forces Aba shoemakers to spend millions on powering generators (part 3)

COVID-19: How transporters, POS money traders rip off interstate, local passengers (PART 2)


One of the workers on-site, nevertheless, told The ICIR that the project embarked upon by the state government was a smaller part of the contract being executed by the Federal Government.

Mbaise axis of Owerri-Umuahia Road
Mbaise axis of Owerri-Umuahia Road

The PODE also named the rehabilitation of sections 1, 2 and 3 of Owerri-Umuahia Road among the projects executed by the Muhammadu Buhari administration in the South-East region. This road connects Umuahia, the capital of Abia State, to Owerri, the Imo State capital, through  Ahiazu Mbaise Local Government Area.

Read Also:

According to information on the Federal Ministry of Works website, the project is handled by Zerock Construction Nigeria Limited.

The reporter did not see any contractor on-site when he travelled through this road in December 2021. The Umuahia section of the road was tarred, but Ubowo to Ahiara in Ahiazu Mbaise Local Government did not look rehabilitated. Residents said they saw contractors in 2019 working at Nguru, Aboh Mbaize Local Government Area, but one of them concluded that the company did a shoddy job. The reporter saw several potholes along the Mbaise axis.

“Well, you can see the state of the road now. We need to start taking infrastructure projects seriously in Nigeria if we want to change the poor state of our nation,” Ugo Amanze, a secondary school teacher from Mbaise, said.

The PODE also listed the rehabilitation of Oba-Nnewi-Okigwe Road as one of the activities of the Buhari administration in the region. The road links Okigwe in Imo State from Traffic Light in Nnewi, Anambra State.

South East projects

The reporter travelled through this road but did not see any contractor or road rehabilitation equipment. Residents, however, testified that a contractor rehabilitated the Nnewi part of the road in 2020.

The rehabilitated part of Nnewi-Okigwe Road
The rehabilitated part of Nnewi-Okigwe Road

But there was no evidence that the road was rehabilitated in any way, as potholes dotted the Nnewi North Local Government axis and several other parts of the road.

“It was a poorly executed project,” a resident of Nnewi, Daniel, said.

The Ozubulu portion of this road wore a bad look, and two residents dismissed the question when the reporter asked them whether work was done on that axis by a Federal Government contractor or not.

“You journalists are the problems of this country,” retorted one of them, Anyanwu Josephine, a native of Ozubulu.

“Does it look like a project was done on this road?” she asked, scurrying away.

The PODE cited ‘more than 60 federal road and bridge projects’ being executed in South-East by the Buhari administration. Simple checks showed that the presidential office repeated exactly the claims made by Lai Mohammed in 2018, which were fact-checked here.

South-East Projects

All the roads listed by PODE in the new claims had earlier been named in Mohammed’s claims.

The ICIR travelled through all of those roads again to ascertain whether they had been rehabilitated. One of such roads was Olokoro-Alaukwu-Itaja-Okwu-Obuohia-Ikwuano Road, contracted to Abia Rhas in 2010. The contract was awarded at N990.673 million, according to information on the Federal Ministry of Works website.

Umuahia-Ahiakwu Road
Umuahia-Ahiakwu Road

Findings showed that this project was started and completed by the immediate past government of Goodluck Jonathan. It was not ongoing and was not done by the Buhari government, which makes the claim misleading.

Next was the Olokoro-Isiala-Oboro-Nnono Road Junction Road. This road was awarded to Abia Bok Company at N515.315 million by the immediate past government of Goodluck Jonathan. Residents said it was completed in 2013, meaning that the Buhari administration neither awarded it nor was it ongoing when the reporter visited it. Also, Umuahia-Ahiakwu-Amangwo Road was started and completed by Jonathan, and not Buhari.

“This road was done by the last administration. It was completed around 2014. It has nothing to do with Buhari,” 71-year-old Thadeaus Ohima, who is a native of Umuahia, told The ICIR.

Next is the Umuna-Ndiagu-Agba Umuna-Ebenebe-Amasi Awka Express Road with Spur  from Umuna – Ndiagu.  The Amansea section of this road was supposed to be constructed by Conduc Nigeria Limited, the contractor listed by the Federal Ministry of Works, but this was not the case.

Part of the Ebenebe town was rehabilitated, but work stopped mid-way. The road from Ebenebe to Umuna was abandoned, so it was not ongoing as claimed by PODE.

“We have suffered on this road, but it gets worse during the rainy season. People can tell you anything they want, but the truth is that this road has been abandoned for many years -even before 2015 when Buhari came to power,” Sunday Ede, who hails from Amansea, told The ICIR.

Ebenebe axis of Umuna-Ndiagu-Agba Umuna-Ebenebe-Amasi Awka
Ebenebe axis of Umuna-Ndiagu-Agba Umuna-Ebenebe-Amasi Awka

South East project

The PODE also referred to Mbaise-Ngwa Road, which connects the Imo River. The reporter saw no contractor when he visited, though the project was listed on the website of the Federal Ministry of Works as being executed by Mangrovetech Nigeria Limited. The ICIR was told by residents that it was completed by the immediate past government of Jonathan.

“It was completed before 2015. Anybody who tells you otherwise is deceiving you,” a passer-by, Okechukwu, who hails from Ngwa, said.

Ngwa-Imo River

The PODE equally claimed that the Buhari government was rehabilitating the Bende-Arochukwu-Ohafia Road. The ICIR reporter found that work was going on at the site from Ohafia. However, this road is divided into various sections. Contrary to PODE claims that all were being rehabilitated, the Nkporo-Abiriba-Ohafia Road was found to have been executed by Abia State government with evidence hyperlinked here.

Ohafia axis of the Bende-Arochukwu-Ohafia Road being constructed
Ohafia axis of the Bende-Arochukwu-Ohafia Road being constructed

The Umuahia-Bende axis, as claimed in PODE’s list, was not going.

In line with PODE’s claim, the Ibinta-Okigwe axis was being constructed when the reporter visited. The only challenge was the quality of the road, said, residents. Of equal importance is the Nenwe-Mburumbu-Nara Road, which Arab contractors handle. The reporter found that work was going on as claimed by PODE. However, residents said it had been a ‘start-stop project,’ meaning that construction has been irregular.

|”They stopped for two years and started again two weeks ago,” a commercial motorcyclist, Chima Anozie, who is from Nara, told The ICIR.

Ongoing Nenwe-Nara-Nome Road
Ongoing Nenwe-Nara-Nome Road

Another resident, Adaku Nnaji, said she was happy that work had re-started on the site.

She urged the contractor to complete the project before the rainy season of 2022.

The Onitsha-Awka Expressway is also one of the projects claimed to be executed by the Buhari administration. The ICIR found that work was going on in December 2021. However, this work had been on for close to 15 years now, meaning that two or three previous governments had been involved in its rehabilitation yet could not complete it.

“I remember it was President Musa Yar’Aadua that awarded it in 2008/09, but it was not completed until he died,” a resident of Awka, who uses the road, Chinwe, said. She regretted that the road had been used to woo voters from the South-East region during general elections.

“Once election comes, they (politicians) will promise to complete it, but they forget their promise after the votes are cast,” she further said.

The reporter found that only one part of the road was done. Work stopped in 2019 after Arroma Junction in Awka, Anambra State capital. No work was done after the Government House in Awka, resulting in a series of accidents, residents said. The reporter found that the Amansea section of the road had been abandoned, eliciting angry reactions from residents.

“This place has been like this for over 10 years now, no work, nothing,” said Adanna Ihuoma, a native of Amansea, who used a stream of expletives on the Federal Government for ‘abandoning the road.’

South-East Projects

She berated the reporter for “not telling the government the truth” even though she was told that the journalist was on a fact-finding mission.

Similarly, PODE claimed that the Second Niger Bridge was ongoing. The claim was found to be true.

More so, Aba-Ikot Ekpene Road claimed to be rehabilitated by Buhari has the signature of the Abia State government. Due to its deplorable state, the Abia State government, in October 2021, “directed the immediate fixing of the deplorable state of the Umuahia- Ikot Ekpene federal road, which has become a death trap.” This was one month after PODE’s claims.

South-East Projects

Completed projects

Some of the projects listed by PODE were discovered to have been initiated and completed by Buhari’s government.




     

     

    Completed Umuahia Tower-Port Harcourt Road
    Completed Umuahia Tower-Port Harcourt Road

    One is the Umuahia Tower-Port Harcourt Road. This project, handled by Setraco Nigeria Limited, had been completed when the reporter visited. The same result was also found at the Old Enugu-Port Harcourt Road. The PODE claimed it was ongoing, but it was discovered to have been completed.

    Similarly, Onitsha-Owerri Road has been rehabilitated as claimed by PODE, including the Okija-Oguta section. This is also the same for Ekwulobia-Oko Road in Anambra State and Uburu Nenwe Road in Ebonyi State.

    Also, Enugu-Port Harcourt Road has been rehabilitated.

    Conclusion

    The PODE claimed that the projects were either ongoing or completed. But out of the 27 projects investigated, only five were completed by President Buhari. Six were ongoing, while two were done by the Abia State government. Three were partially done. No work was recorded on six projects. However, four projects were completed by Goodluck Jonathan, and one was suspended. This means that only 15 out of the 27 projects recorded some form of execution by the Federal Government.

    Join the ICIR WhatsApp channel for in-depth reports on the economy, politics and governance, and investigative reports.

    Support the ICIR

    We invite you to support us to continue the work we do.

    Your support will strengthen journalism in Nigeria and help sustain our democracy.

    If you or someone you know has a lead, tip or personal experience about this report, our WhatsApp line is open and confidential for a conversation

    LEAVE A REPLY

    Please enter your comment!
    Please enter your name here


    Support the ICIR

    We need your support to produce excellent journalism at all times.

    -Advertisement-

    Recent

    - Advertisement